Table
of Contents
GETTING STARTED
Determining Your Classification
Should I Hire a Construction Manager?
Should I hire a Prime or Main Contractor or
act as Owner-Builder
Owner Builder Project Types
Construction Management Contract
Identifying Major Phases of the Work
Organizing a Project
Project Information Form
Project Directory
My Project Organizer Roles
Glossary Search
BUDGETING/ESTIMATING
Budget For Savings & Understanding
the Estimate
Establish a Project Budget
Identify, Organize and List Cost/Budget
Components
Cost Classifications
How Much Contingency is Enough?
CALCULATORS
Calculate a Budget/Estimate with or without
markup
Calculate General Requirements
Calculate Preliminary Budget/Estimate
BONDING & INSURANCE
To Bond or Not To Bond?
Insurance To Limit Liability
Limits of Insurance
Certificates of Insurance
SCREENING & QUALIFYING PROFESSIONALS
Architect, Designer and/or Engineer(s) Hiring
Guidelines
Screening Architects, Designers and Engineers
Screening or qualifying a
Construction Managers and Contractorss
SCHEDULING
Schedule Definitions
Project Calendar
BIDDING
Bidding for Responsiveness, Dependability and
Value
Prepare and Submit RFPs
Verbal Quotation Form
PROJECT ADMINISTRATION & CHECKLISTS
My Project Organizer
Protecting Property Against Liens
Project Administration Checklist
Pre-Construction Check List for
Contractors and Owner Builders
Pre-Construction Meeting Agenda
Building Planners Checklist
Drawing Review Checklist
Site Plan Review Checklist
Should
I Hire a Construction Manager:
The best way to answer this question is to decide
if you really understand what is involved in handling your particular project.
Keep in mind that every project is unique and therefore has its own set of
circumstances. Whenever you undertake a construction project whether it's the
replacement of a door in your home or the building of a commercial facility the
construction management process is used. Here are the steps taken and questions
asked for every construction project, big or small, simple or complex:
Define the problem or specific objective and don't overlook simple questions
like "is it really broken?"," should it be remodeled?" or "do I need a new
building?", and Solve the problem by determining how to achieve the objective
by asking simple questions like:
- How will I get it done?
- Who should be involved in my project?
- When is the best time to start my project?
- When do I want my project completed; and
- How much will it cost or how much am I willing to spend?
Before answering these questions we must understand
the available construction options, professional relationships and roles.
First let's look at available construction options, they are:
Design Build: When a prime or main contractor bids or negotiates a
project with the owner to provide both design and construction services on a
specific project. The prime or main contractor performs as an independent
contractor and this concept can save time and costs over the traditional
Contractor and Architect concept;
Traditional Contractor and Architect Concept: When a prime or main
contractor bids or negotiates the construction of the entire work AFTER the
design and final plans and specifications are complete. The prime or main
contractor performs as independent contractor and this concept usually costs
more and takes longer;
Fast Track Construction: When a prime or main contractor, or
construction manager (CM) at-risk negotiates to start a construction project
BEFORE the plans and specifications are complete. The contractor or CM at-risk
performs as Independent Contractor. This option is generally used on very large
projects and can expedite the completion time but costs are continually
adjusted as the design progresses; and many property owners are not aware of a
construction process available to them that can save them thousands of dollars,
lots of time, and allow them to achieve ultimate project control, which is:
Should I hire a Prime or Main Contractor or act as Owner-Builder :
Owner-Builder as Prime or Main
Contractor. When the owner takes on the responsibilities of
the prime or main contractor to build a specific project. This option
gives the owner ultimate control over schedule and costs especially
when employing a construction manager for fee as the owner's agent.
By contracting directly with licensed specialty contractors the
Owner-Builder can:
1. Save money because the general contractor marks up the specialty
subcontractors actual bid price and then adds other fees such as
overhead, profit and general conditions. All of these fees and mark
ups can be substantial. Unless you have a cost plus contract with
the general contractor and are entitled to see actual subcontract
agreements, material receipts and actual labor time sheets you never
know how much a project really costs; and
2. Have direct control over the specialty contractors costs, schedule
and work quality because you will see and approve actual invoices,
schedule results, and work in place quality before releasing any
payments. Answering YES or NO to the following questions you could
determine if this Owner-Builder process is right for your next construction
or alteration project:
Click
here to use form
A YES answer to all of these questions probably
makes you a good Owner-Builder candidate. However, those who can't answer YES
can still take advantage of this Owner-Builder process. The owner can still
have ultimate control over schedule and costs by hiring a Construction Manager
for fee who basically acts as his/her agent. Some Construction Managers will
help set up a project and/or work on an as needed consulting basis. This gives
the owner the best of both worlds because Construction Managers are required to
be licensed by the Contractors License Board and Construction Management fees
are generally substantially less than a General Contractors combined specialty
contractor mark ups plus his/her overhead and profit. Also, the Construction
Manager for fee, acting as the owner's agent, owes a client a "Fiduciary Duty"
(Trust). Whereas, a General Contractor is an independent contractor who is free
from the influence, guidance, or control of another or others and does not owe
a "Fiduciary Duty".
Next look at the professional relationships of the parties. It is important to
understand if a contractor or professional is an Agent or Independent
Contractor.
Agent: One authorized by a client (principal) to act in his/her stead or
behalf and owes the client a "fiduciary duty" (Trust). Example: Construction
Manager for fee but classified as an independent contractor for tax purposes. A
construction manager for fee has limited or no financial responsibility whereas
a construction manager at-risk does have financial risk similar to a general
contractor; and
Independent Contractor: One free from the influence, guidance, or
control of another or others and does not owe a "fiduciary duty". Example:
architect, engineer, prime or main contractor, construction manager at-risk.
Owner Builder Project Types:
The following three-owner/project types usually use
one or more licensed specialty contractors. Using the Owner-Builder process can
prove extremely beneficial on these types of projects because these licensed
specialty contractors can usually be easily coordinated and their scope of work
defined without risk or conflict.
Click
here to use form
Construction Management Contract:
A comprehensive construction management contract
covers five Major functions:
- Cost Management, including estimates of construction cost and development of
project budget;
- Scheduling, often incorporating critical path method techniques, for all phases
of the project;
- Design review, including review of formal design submissions and overall
construction feasibility;
- Bid packaging and contractor selection; and
- On-site management to provide supervision, inspection, and administration.
Construction Management Companies are listed in the Yellow pages of your
telephone directory under the heading of "Construction Management". Some
General Contracting firms have the capability of performing construction
management services.
When selecting a Construction Manager or
Construction Management firm request a written Construction Management
proposal. The proposal may include all or some of the following depending on
the size and complexity of your building project:
- Master Planning services, which would include project budget information and
scheduling.
- Construction Management Services, which would include systems and procedures,
cost management, time management, general consulting, affirmative action and
community relations, and on-site management.
Some advantages of using a construction manager
are:
- His/her knowledge of the construction process;
- Direct control over payments made to the contractor(s) (the ability of paying
actual costs plus agreed upon markups);
- Direct control of subcontractors and Material persons;
- Direct control of schedule;
- Ability to negotiate directly with subcontractors when changes in the work are
required or if unforeseen conditions are discovered;
- Minimize the threat of liens by paying subcontractors and material person
directly;
- Having the option of using a general contractor or doing the project as
owner-builder;
- His/her knowledge of owner's and contractors rights and obligations during the
building process and proper transferring of risk.
Identifying
Major Phases of the Work:
This is a checklist of essential and commonly used activities and
tasks for any project broken into the following twelve (12) phases:
- Project Development
- Project Organization
- Design for Gathering
- Conceptual Design and Planning
- Preliminary Design
- Contract Documents
- Bidding for Performance
- Award Contracts
- Construction Phase
- Close Out
- Occupancy
- Operational

Organizing
your Project:
This form helps you gather answers to the following questions:
- How will I get it done?
- Who should be involved in my project?
- When is the best time to start my project?
- When do I want my project completed; and
- How much will it cost or how much am I willing to spend?

Click
here to use form
The form links you to project directories, scheduling
terminology, and budgeting/estimating calculators.
Project
Information Sheet:
This form helps you gather basic information about your project. It is not
intended to be a Project Directory, but rather a quick reference of key project
members and overall project objectives during the planning phase of the
project. It is useful for selecting and identifying major team members for your
next project.

Prepare
and Maintain a Project Directory:
To keep track of who's involved prepare a Project Directory. A Project
Directory is important for the purpose of listing all persons and/or companies
contacted and/or being considered for the project. The preliminary directory is
generally completed in long hand or an electronic data base as the respective
project contacts are made and being selected for consideration. The directory
keeps all contacts in one location for fast reference.
| Communication
Tip! |
Keep a copy of this directory in a central
location so that anyone associated with your project can have access to it for
quick reference. |
|
Productivity
Tip! |
Keep a copy of the preliminary
directory containing all contacts whether they were actually selected on not.
It will save a lot of time in the future because you will have names and
addresses of individuals and companies that may prove useful on future similar
projects. |
|

Budget
for Savings and Understanding the Estimate:
A Budget gives you a handle on how much you are willing to spend for the
project.
Before establishing a budget it is important to understand the limitations of
estimating. An estimate is defined as a forecast of construction cost, as
opposed to a firm proposal; whereas construction estimating is a forecast of
construction costs prepared on the basis of a detailed analysis of materials,
labor, equipment for all items of work by multiplying the volume by costs per
unit or measurement, and finally an approximate evaluation of the finished
product. In either case a construction cost estimate is a forecast based on
designed and planned items.
At the onset of a project planned items do not exist. Therefore, early
conceptual budget planning is essential for establishing a target range for
monitoring performance as the project progresses. Also, this conceptual budget
can serve as a basis for continuous in progress revisions to insure that the
original overall budget objectives are not being overlooked. Those who
understand this process will experience an easier time working with the project
team members as the project is executed.
Establish
a Project Budget:
Before making a budget the following actions must be taken:
The project must be identified and a preliminary Scope of Work for the project
must be completed. Here are simple scope of work outlines for large or small
projects. The idea is to begin gathering information about your project and
putting it in writing.
Small
Project |
Project statement or identification:
Replace back yard fence
Preliminary Scope of Work:
Hire a contractor to remove and dispose of an existing fence; supply all labor,
materials and equipment necessary to install a new fence. |
|
|
Large |
Project statement or identification:
Build new office facility
Preliminary Scope of Work:
1. Complete a feasibility study
2. Purchase land
3 Hire construction consultants (Architects, Engineers, Construction Manager,
etc.)
4. Build a new building complete with interior improvements and furniture
5. Sell the building |
|
|
Identify,
Organize and List Cost/Budget Components:
It is good practice to organize your project and cost components using a widely
accepted construction industry format. The MASTERFORMAT published by The
Construction Specifications Institute (CSI) has been widely accepted as an
industry standard in the United States and Canada since 1963. The numbers of
MASTERFORMAT are organized into 16 basic groupings of related construction
information called "divisions.
This MASTERFORMAT provides the specifications writer with a standard yet
flexible system for writing specifications at various levels of detail as
needed to meet the project's needs.
Cost
Classifications:
Familiarization with the MASTERFORMAT allows the users to easily
relate a specification section with both product information and
cost data. The following describes how job costing or job budgeting
can be organized using the MASTERFORMAT division
Division 1 - General Requirements can be used to accumulate costs
for temporary construction facilities and controls, mobilization,
job site administration, and other general requirement cost items;
Divisions 2 - through 16 can be used to accumulate
applicable project costs related to products and their installation;
How
Much Contingency is Enough?
Contingency is defined as a sum designated to cover unpredictable
or unforeseen items of work, or changes subsequently required by
the owner.
The table below indicates possible contingency items and their corresponding
variations through various project phases. These contingencies are
to be applied to the known identifiable items of cost at each stage.
These percentages should be determined and agreed to by all respective
project team professionals. The percentages should include factors
for experience and judgment limitations, and represent probable
additional budget requirements in addition to those which are definable
at the beginning stage of project development. Therefore, it is
likely that the percentages will vary between firms and projects.
With contingencies determined, each member of the project team can
better understand his/her responsibility in maintaining the overall
project budget.
Maintain a "the budget cannot be exceeded" attitude. Agree at the
start if various contingencies are exhausted either the budget will
be revised (if approved by the owner), the design will be altered
or a creative alternative will be developed.
The following is a good guide for determining the amount of contingency
(per cent of total project cost) to allow for depending on the phase
the project is in:
This table illustrates that the contingency could be as high as
25 per cent at the beginning of the project before starting the
Pre-Design Phase; and could be as low as 3 per cent before starting
construction.
The amount of contingency has a direct relationship to the amount
of known information in connection with the project. The less amount
of information known the greater the contingency. And conversely,
the greater amount of information known the lesser amount of contingency
is needed.
CALCULATORS
Calculate a Budget/Estimate with or without markup:
See Budget for Savings and Understanding the Estimate
This calculator can be used with the Preliminary Budget/Estimate calculator or
as a stand-alone calculator. This calculator has the following optional
features:
Calculate Mark (useful for contractors and vendors)
Calculate contingency (useful for building owners, contractors and vendors)

Calculate General Requirements:
See Budget for savings and Understanding the Budget
General Requirements are often overlooked or not completely tabulated and these
costs are frequently substantial depending on the size and overall scope of the
project.
Therefore, this calculator includes a list of the most commonly used tasks and
activities within the following categories:
- Non-Distributable Labor
- Permits and Fees
- Temporary Services
- Other General Requirements
- Insurance and Bonding
- Other Overhead and Contingency
- Project Closeout
Calculate a Preliminary Budget/Estimate:
See Budget for savings and Understanding the Budget
This calculator has the following features:
1. It is organized in a format substantially paralleling the MASTERFORMAT
published by The Construction Specifications Institute (CSI). The numbers of
MASTERFORMAT are organized into 16 basic groupings of related construction
information called "divisions." The CSI numbers and titles of the divisions
are:
- General Requirements
- Site Work
- Concrete
- Masonry
- Metals
- Wood and Plastics (Carpentry)
- Thermal and Moisture Protection (Building envelop items)
- Doors and Windows
- Finishes
- Specialties
- Equipment
- Furnishings
- Special Construction
- Conveying Systems
- Mechanical (HVAC, Plumbing, etc.)
- Electrical, Data, Voice
- Other
NOTE: To make the form more flexible we have excluded the Division
numbering in the Calculator.
2. The form has an optional OVER or (UNDER) Budget/Forecast column for
calculating and determining if you're actual or committed costs are OVER or
(UNDER) your original budget amounts.
3. The form makes it easy to gather costing information from a list menu
containing the following options:
- Bid form in response to an RFP (The Base Bid/Estimate Amount value from the selected BID FORM)
- Bid Tabulation Form (The selected Base value for the selected BID TABULATION FORM)
- Calculator (The TOTAL for the Budget/Estimate with or without markup
calculator)
- Internet (An editable page of your favorite cost information links on the internet)
- Manual Entry (Allows you to manually enter a cost value.
BONDING & INSURANCE
To
Bond or Not to Bond
Should I require a bond for my project?
Recognize that a bond adds cost to the overall project costs. It is like an
insurance policy for the purpose of guaranteeing the contractor(s) performance
to complete work and insure that the contractor pays his employees and material
suppliers with the money you pay the contractor.
If you have pre-qualified the contractor (see How do I Screen and Qualify
Contractors?) and you are comfortable with his/her capabilities you may want to
save the cost of the bond.
| Tip! |
Regardless if you decide to purchase
the bond or not it is a good idea to determine if the contractor is Bondable,
what his/her Bonding Rate is, and what his/her Bonding Capacity is. |
|
Bondable - What does it mean?
A contractor is bondable when a rated surety company has given the contractor a
written statement of bond ability. Before issuing such a statement the surety
company conducts their own background check on the contractor before they make
a commitment to provide a bond to the contractor. When the surety company is
satisfied that the contractor is a good risk the contractor becomes bondable.
Bonding Rate - A Useful Contractor Qualifying Tool:
When the contractor becomes bondable the amount the surety company charges the
contractor for the bond is called the bonding rate. This bonding rate is based
on the risk factor the bonding company places on issuing the bond to the
contractor. The higher the risk to the bonding company the higher the bonding
rate.
And conversely, the lower the risk to the bonding company the lower the bonding
rate.
The bonding rate is a good guide for comparing contractors by looking at their
bonding rates you can generally tell if the contractor has a good track record.
Example: Contractor A has a bonding rate of 1% (one per cent) whereas
contractor B has a bonding rate of 3% (three per cent). Contractor A has a
greater experience level and capabilities than contractor B as viewed by the
Bonding Company. Also, contractor A's bond will cost you 2% less than
contractor B's bond.
Bonding Capacity - Why is it important?
The bonding capacity is the dollar amount the bonding company is willing to
guarantee for all bondable and non-bondable work the contractor has on hand
based on the experience level and capabilities of the contractor. Example: The
bonding company determines that the construction company qualifies for a
bonding capacity of $2,000,000. The contractor has work on hand, contracts
totaling $1,000,000 ($500,000 requiring bonds and $500,000 not requiring
bonds). In this example the contractor has a bond surplus of $1,000,000 for any
future work requiring a bond.
Example: The bonding company determines that the construction company
qualifies for a bonding capacity of $2,000,000. The contractor has work on
hand, contracts totaling $1,000,000 not requiring bonds. The contractor wants
to bid on a new $2,000,000 project requiring a bond which would increase his
work on hand to $3,000,000. In this example the contractor has a bond deficit
of $1,000,000 and will not be granted the bond unless the bonding company
reevaluates the contractors capabilities and agrees to increase the
contractor's Bonding Capacity.
| Tip! |
If you are requiring a bond ask the
contractor to invoice you for it's direct Cost. You'll save a hefty mark-up. It
is not necessary to include the bond cost in the contract schedule of values
and incur the contractor's markup. |
|
Insurance
to Limit Liability:
What type of insurance should I have on my project? It is the writers opinion
that every project you undertake should be properly insured. Generally, all
construction contracts will have a section on insurance stating the property
owners and the contractors insurance obligations under the contract.
IMPORTANT: Insurance procurement requirements written in a contract do not
guarantee that the insurance has been procured, is valid, or coverage is in
force. Therefore, it is very important to obtain Certificates of Insurance
before construction begins. The following is a partial listing of types of
coverage available and who is generally responsible for procuring it:
The PROPERTY OWNER is generally asked to procure and maintain in full force and
effect:
Fire insurance with course of construction, vandalism and malicious mischief
clauses attached; such insurance is generally the sum of at least equal to the
contract price with loss, if any, payable to any beneficiary under any deed of
trust covering the project. The policies may name the contractor and
construction lender as additional insured; and if the owner fails to procure
this coverage the contractor generally has the option of procuring the
insurance as agent for and at the expense of the owner.
The CONTRACTOR is generally required to procure and maintain in full force and
effect:
Worker's compensation and comprehensive liability insurance policies.
Limits
of Insurance:
Worker's Compensation and Employer's Liability Insurance
The limits of worker's compensation are based on statutory requirements by the
respective contractor licensing states. In California, for example, all
contractors are required to procure worker's compensation insurance before a
contractor's license is issued. There is one exception to this requirement. If
the contractor has no employees, an exemption certificate must be submitted to
the Contractors State License Board, certifying under penalty of perjury that
he/she does not employ any person in any manner to be subject to Worker's
Compensation laws of California.
You should contact the Contractor's License Board in your respective state to
confirm this requirement.
Comprehensive General
Liability Insurance
The limits of insurance are generally determined by the architect and/or the
owner and are usually written into the specifications for the project. Your
insurance requirements could look like this:
Certificates
of Insurance:
| Tip! |
Always demand certificates of
insurance from the contractor before he/she starts the work. |
|
| Tip! |
Verify General Liability and Workers
Compensation insurance certificates from the contractor prior to starting
construction. Examine the policies expiration dates and be satisfied with the
amount of coverage the policies offer; also insist on getting a copy of the
certificate for your file. Otherwise, you may have considerable liability. |
|
SCREENING & QUALIFYING PROFESSIONALS
Architect, Designer and/or Engineer(s) Hiring Guidelines:
It is not uncommon to wonder if you really need an architect, engineer
or designer for a particular project.

Screening
Architects, Designers and Engineers:
Some of the core essentials that may form a basis for screening Architectural
and Engineering professionals are found by completing a form.

Screening
or qualifying a Construction Manager or Contractor:
You can screen and qualify Construction Managers or Contractors by collecting
background information from them.
The following Contractor Qualification Statement questions should be completed
by the Contractor and returned for your review. It is a good idea to obtain
Qualification Statements from at least three contractors for your specific
project and it is not uncommon to qualify six contractors for a given project.
However, some contractors are reluctant to bid on projects when more than six
contractors are bidding on the same project because they feel that their odds
of being low bidder have been reduced. As an Owner your objective is to qualify
contractors for your specific project. Therefore, you should develop reasonable
bidding parameters based on the scope and budget for your project.
If you are performing a minor remodel you will probably want to qualify at
least three contractors. And if you are planning to construct a new home of
office building you probably want to qualify at least six contractors.
Upon qualifying the contractors you can establish your approved contractors
list and from this list you either negotiate or bid your project.
The following is a partial list of questions contained in this Contractor
Qualification Statement and a brief explanation of their importance:

Prepare
a Schedule:
A Schedule forces you to plan when you want to start and complete the project
and how you want it controlled.
Schedule
Definitions |
ITEM |
DEFINITION |
| Activity |
The smallest work unit within a
project; the basic building block of a project. |
| Bar Chart |
A Bar Chart shows the start and
finish dates using horizontal lines to represent the activities duration. |
| CPM (Critical Path
Method |
A planning, scheduling and control
technique whereby a construction project is completely planned and scheduled
and an arrow diagram drawn to show the interconnected individual tasks involved
in constructing the project. CPM concentrates on the tradeoff between the cost
of a project and the time needed to complete it. |
| Critical Path |
The set of activities that must be
completed on time for the project completion date to be met. Activities on the
critical path have no slack time. |
| Currant Date Line |
A vertical line on the chart
indicating the currant date. |
| Duration |
The length of an activity, excluding
holidays and other non-working days. |
| Finish Date |
The date that an activity or project
is completed. |
| Gantt Chart |
The schedule of activities for a
project. A Gantt Chart shows start and finish dates, critical and non-critical
activities, slack time, and predecessor relationships. |
| Milestone |
An activity with a duration of zero
(0) and by which progress of the project is measured. A milestone is an
informational marker only; it does not affect scheduling. |
| PERT (Program
Evaluating and Review Technique) |
A project planning and reporting
that is useful in situations where it is difficult to accurately estimate the
time needed for individual activities. |
| PERT Chart |
A type of flow chart showing the
order and interrelationships of a project's activities. |
| Predecessor |
An activity that must be completed
before another activity can begin. |
| Slack Time |
The flexibility with non-critical
jobs that allows their start dates to be adjusted without affecting the project
completion date. |
| Start Date |
The date that an activity or project
begins. |
| Successor |
An activity whose start depends on
the completion of one or more predecessors. |
|
| Tip! |
Request a construction schedule
prepared by the contractor incorporating your completion date and your move-in
date. Gives real meaning to the completion of your project. |
|
My
Project Organizer Calendar:
This calendar allows you to keep up-to-date on meetings, task
deadlines, and other important events associated with a construction
project. Each event can be made public or restricted to certain
team members. Task deadlines are automatically linked to a project
calendar. This calendar features a progress bar display alerting
the users about the time remaining for a project deadline.
Bidding
for Responsiveness, Dependability and Value:
The best way of insuring that you are getting the best value for
you scope of work is the get competitive bids and/or estimates
professional contractors, suppliers and resources.
It is important that all bids and estimates are based on the same
information. Therefore, the following forms can be used to distribute
the same information and then receive the same information in
the same format. This make it very easy to compare and analyses
the the bids and estimates that you receive.
Prepare
and Submit RFPs:
RFP means Request for Proposal. This RFP form contains all the essentials for
collecting costing and scheduling information associated with getting a bid or
estimate. This form has the following features:
Send an RFP to a CLOSED group of bidders (a private bid list as selected by
you); or
Send an RFP to an OPEN group of bidders (the RFP will be listed on our site and
anyone can bid on it). Option of having bids returned directly to you using our
BID FORM or sent directly to you without using our Bid Form.
Verbal
Quotation Form:
Even though written communication is stressed and should be the
rule of thumb many contractors (especially subcontractors and
material suppliers) will give verbal quotations or cost proposals
on the telephone. The FAX machine has helped enormously to minimize
this practice.
However, when you do obtain verbal quotations it is extremely
important to obtain all pertinent detailed information about the
proposed transaction this information will become the Terms
and Conditions written into the final contract agreement
and/or purchase order between you and the respective subcontractor.
The Verbal Quotation form in this section has been designed to
obtain that pertinent information necessary for defining and understanding
the scope of work, terms and conditions, and limitations being
proposed by the contractor or material supplier.
This form serves as a checklist for defining and understanding
the scope of work, terms and conditions and limitations being
proposed by the contractor(s) or material supplier(s).
The online version of the form can only be used after an RFP has
been created and only the RFP creator can open the Verbal Quotation
form to enter the data.
PROJECT ADMINISTRATION
& CHECK LISTS
My
Project Organizer:
My Project Organizer is a shard, secure
workplace on Constructionplace.com for distributed project teams
to administer and organize any size project. My Project Organizer
enables the project team to communicate more effectively.
Gaining access to My Project Organizer.
There are two ways of gaining access to My Project Organizer:
- Become a Team Member by invitation:
Upon receiving an email invitation to become a team member from
the organizer of a specific project the invitee must be or become
a registered user of Constructionplace.com. Three registration
options are available. For security purposes registered visitors
are not allowed access to My Project Organizer.
- Become the Creator of a My Project Organizer:
Any registered user except visitors may create a My Project Organizer
at Constructionplace.com and become the project(s) organizer.
The first project is complimentary, and a nominal monthly fee
is charged for additional projects.
My Project Organizer Roles
| Role |
Rights |
| Coordinator (Creator) |
The first person to start and create
the My Project Organizer service. The creator is usually the Coordinator. The
creator may do the following:
- Assigns the Coordinator role to any other registered constructionplace.com
person
- Assigns more than one Coordinator for a given project
- Creates the first project within My Project Organizer
|
| Coordinator |
Has full access to all content
within a My Project Organizer. The coordinator is responsible for:
- Team Member Management and Invitations
- Creating groups within a team· Setting member permissions
- Managing settings, changes and status
- Controlling access to items and content
|
| Team Member |
Can create new items, and read and
edit other Team Member items subject to permissions given by the Coordinator. A
Team Member is also known as a Participator. |
| Observer |
Can monitor activities and content
in My Project Organizer, but cannot participate. |
|
Protecting
Property Against Liens:
Discharging of Lien(s) or Claim(s):
The following wording can be incorporated into a contract to protect your
property against Liens or Claims:
If at any time there is evidence that a claim which is chargeable to CONTRACTOR
or a SUBCONTRACTOR, is or may become a lien against the premises, OWNER may
retain out of the contract price an amount sufficient to indemnify it against
such claim or any lien growing out of such claim and against all costs and
expenses (including attorney's fees) which OWNER incurs or may become obligated
to pay in connection with said claim or lien or arising out of any action
relating thereto.
If payment of the contract price has been made to CONTRACTOR hereunder
CONTRACTOR shall immediately reimburse OWNER for all moneys, costs, expenses
and disbursements (including attorney's fees) that OWNER may be compelled to
pay to discharge such lien or claim on or against said property.
Procedure for obtaining lien releases during
construction covering progress payments:
Commencing with the first progress payment request, CONTRACTOR shall submit a
CONDITIONAL WAIVER AND RELEASE UPON PARTIAL PAYMENT covering all approved
scheduled payments to respective subcontractors, material suppliers, and
contractor's general conditions;
Commencing with the second progress payment request and all subsequent progress
payment requests, CONTRACTOR, SUBCONTRACTORS and MATERIAL SUPPLIES shall submit
via the CONTRACTOR appropriate affidavits and wavers and releases as follows:
Subcontractors and Material Suppliers shall submit UNCONDITIONAL WAIVERS AND
RELEASES evidencing payment by the CONTRACTOR for all labor and materials
covering the previous payment request; and
CONTRACTOR shall submit a CONDITIONAL WAIVER AND RELEASE UPON PARTIAL PAYMENT
covering all approved scheduled payments to respective subcontractors, material
suppliers, and contractor's general conditions.
Procedure for Obtaining Lien Releases Prior to Making
Final Payment:
Contractor, Subcontractor and Material Suppliers shall submit via the
CONTRACTOR appropriate affidavits and wavers and releases as follows:
Subcontractors and Material Suppliers shall submit UNCONDITIONAL WAIVERS AND
RELEASES UPON FINAL PAYMENT evidencing payment by the CONTRACTOR for all labor
and materials covering and associated with OWNER'S project; and
CONTRACTOR shall submit a CONDITIONAL WAIVER AND RELEASE UPON FINAL PAYMENT
covering all approved contract costs.
Project
Administration Check List:
This form contains a very basic checklist of things to think about before
starting your next project. These items may or may not be relevant to your
project, but are intended to stimulate questions on how to set up project
administration priorities for your next project. Constructionplace.com offers consulting services to assist in setting up project administration
procedures.
Pre-Construction
Check List for Contractors and Owner Builders:

Pre-Construction Meeting Agenda:
This form contains commonly used items to think about in preparation
of holding a pre-construction meeting. Pre-construction meetings
generally focus on items and activities requiring completion prior
to the start of construction, and overall project expectations.
The form can be modified to add some of your own descriptions.

Building Planners Check List:
This form contains commonly used resources, activities and functions used on
construction projects. Use this form to create a working checklist of items
associated with you next project. The form has the following sections:
- Design, Engineering, Construction Management and Support Professionals
- Services
- Off-Site Improvements
- On-Site Improvements
- Exterior Utilities and Connections to Buildings
- Exterior Identification and Lighting
- Building Shell - General
- Building Shell - Flooring, Ceilings, Partitions, Interior Painting
- Mechanical and Electrical
- Energy Costs
- Interior Furnishings and Furnishings
- Landscaping
- Materials and Equipment - General
- Home Improvement Items for Selling

Drawing Review Check List:
This form contains general items for checking a set of architectural
drawings.
Site Plan Review Check List:
This form contains general items for checking a Site Plan of a set
of architectural drawings.

|